SCHEDULING COMPUTATIONS
The following page contains the same precedence network and calendar
for the structural bracing of a typical floor in a building expansion project used in
homework 3. This assignment is identical to homework 3, but now you will apply numerical
computations to arrive to your results. Show your work!
- Perform all the scheduling computations for each activity. Show early dates, late dates,
and floats on the network diagram. Mark the critical path.
- Using the attached blank grid, develop a bar chart with all activities placed in their
early times. Also show with a thinner line the late time for each activity. Take into
account the working calendar.
[Images mentioned above]
|