|


| |
ACTIVITY NETWORK DEVELOPMENT
You are planning for the tennis court sketched below. The activity list
has been identified and is also presented below.
The construction will follow this sequence:
- The permit is required prior to starting any construction activities.
- The entire area must be prepared first.
- The court area must be paved, overlaid, and cured. After this, painting, fencing, and
installing the judges stand and nets can be done in any order, at any time.
- The bleacher area must be paved after the court is paved (court curing is not required
to be done). Then bleachers and stand can be built in any order, at any time.
- Stand equipment must be installed after stand is painted.
Develop a suitable activity network for this project.
[Image of tennis court sketch]
|