Tentative Schedule of Activities
|
January 2004 |
Planning Meeting at CSU (ACRC Reihl Conference
Room): January 28, |
|
March 2004 |
Laboratory tests of combined experimental systems and
tests with calibration aerosols (NOAA-Aeronomy): March 15-26 |
|
April 2004 |
Intensive Operations Period at Storm Peak Laboratory |
|
May 2004 |
Deployment during periods of opportunity |
|
June 2004 |
Equipment removal |
|
Summer 2004 – Summer 2005 |
Analysis of field data and EM grids; Supporting
additional laboratory studies; Quarterly meetings to coordinate analyses;
Initial preparation of journal articles |